The inspection finds problems in the rest of the Mexico City subway line


0

Visual inspection found problems on about a third of the elevated subway line in Mexico City, where one span collapsed on May 3, killing 26 people.

MEXICO – A visual inspection identified problems on about a third of the elevated Mexico City subway line, where one span collapsed on May 3, killing 26 people.

The study of the Faculty of Engineering on the city line number 12 covered 12 kilometers of elevated path, but not the section that collapsed.

A previous report released Wednesday on the collapsed section found construction defects from the time the railway was built in 2010-2012, but those defects were hidden and are unlikely to be seen in a visual inspection.

What the engineers saw on the rest of the line in a study released Thursday were cracks in poles and support beams, crooked brackets, rainwater leaks and metal beams that may not meet standards because they are welded in the middle or not resting properly on rubber shock absorbers.

Shock absorbers are needed in earthquakes prone to Mexico City, and the beams must have room to move without hitting the concrete girders, which was also lacking in some places.

It was said that the shortcomings must be further studied, perhaps by examining concrete samples or studying steel welding. He did not classify the shortcomings as extremely serious, but recommended that they be studied before reopening the line.

The report says the other two-thirds of the line appears to have worn out quite normally.

What was surprising was that although some of the problems may have been the result of normal use or earthquakes, many of them were clearly visible and the errors resulting from the initial construction of the problematic line seemed to be.

Some brackets – pieces of open-frame metal that were supposed to keep the two main steel track girders evenly spaced – were installed incorrectly or without the necessary bars for transverse fastening. Some of the girders are welded differently than others.

One of the pillars of the elevated path seemed to be built a few inches from the pillar supporting a separate path that runs across it. As the concrete pillars sway in earthquakes, they could slam against each other.

The results add trouble to line number 12, which has been closed since the crash.

In Wednesday’s report, much of the collapse blame was placed on poorly welded joints in the wedges that joined the steel support beams to the concrete layer supporting the track bed. The report also says there are clearly not enough pins, and the concrete poured over them may be defective. The welds between the strokes of the steel beams also appear to be poorly performed.

Since the concrete was poured over the wedges, they would not be seen on Thursday in the inspection.

The problems would fit in with reports that the project was rushed to completion so that subway line number 12 could be opened by current Foreign Minister Marcelo Ebrard before he left the post of mayor of Mexico City in 2012.

Line number 12, worth $ 1.3 billion, the newest part of a large subway system opened in 1969, was unfortunate from the start. The so-called Gold Line cost half as much as anticipated, suffered repeated construction delays and was hit by allegations of design flaws, corruption and conflicts of interest.

The scandal surrounding the forced closure of an expensive new line in 2014 – just 17 months after it was inaugurated – basically forced Ebrard into political exile. He was rescued by his patron, new President Andrés Manuel López Obrador, who helped him become mayor in 2006 and resuscitated him by appointing a foreign affairs secretary in 2018.

Despite the subway scandal, Ebrard was in charge of Mexico’s efforts to procure coronavirus vaccines and was once considered a prime candidate to succeed López Obrador in 2024.

That was until the May 3 accident saw the span of a lofty buckle to the ground, dragging two subway cars.

Experts said the line has suffered from design problems from the start. Unusually sharp curves on the track exacerbated problems with the design of the tire on the wheels on steel.

Subway cars chattered and crashed, and the rails began to take on a wavy pattern. Drivers on some sections had to slow down trains to only 5 km / h. In 2014, the Gold Line had to be closed for months for tracks to be replaced or shaped.

The Mexico City subway, which serves 4.6 million drivers daily, has never had one thing it needs most: money. With ticket prices stuck at 25 cents per ride, one of the lowest rates in the world, the system has never come close to paying its own costs and is dependent on huge government subsidies.

.


Like it? Share with your friends!

0

What's Your Reaction?

hate hate
0
hate
confused confused
0
confused
fail fail
0
fail
fun fun
0
fun
geeky geeky
0
geeky
love love
0
love
lol lol
0
lol
omg omg
0
omg
win win
0
win
Stacy

0 Comments

Your email address will not be published. Required fields are marked *